North Georgia Live Steamers

View Original

The passenger line is now complete - Workday recap for Saturday, September 4, 2021

What an incredible day. After 42 workdays over 14 months of work the passenger line is now complete. Today’s crew consisted of Wes, Gene, “Bob2”, Scott, Norm, David E., and Robby installed the last 55’ of track. They also cleaned up some areas with additional gravel and fill to reduce any drainage issues in the area. Next on the list of to-do’s includes grade crossing lights at the pedestrian crossing along with a switch motor for the station bypass track.

Scott was able to capture the last buck of 57 being dumped on the passenger line project as the crew put the finishing touches on the project. Not sure why Norm is scratching his head other than maybe thinking about what the next project will be.

David E. and Robby took the first ride on the completed passenger line all the way through the new station area. They looked like two kids in a candy store. Just saying.

We did run into an issue with the club diesel towards the end of the day. Let’s just say that the engine is fine but the truck under the sulky isn’t. One of the axles has warn to a point it came out of the side frame. Norm took the truck and is going to get it fixed until them just know the club diesel is not available until the sulky is fixed.

See this content in the original post