Workday Recap for Saturday, October 17, 2020 - Passenger Line and more

We may not be running this year but that has not stopped many of our members in getting ready for 2021. Dan went up to Virginia this week and picked up his locomotive and new powered slug and green riding cars. I think he is up to about 6 or 7 riding cars plus his other rolling stock. Looking forward to seeing the new combination on the rails soon. Dan stopped by the site today to do a little trailer shuffle and will be back to rearrange his big trailer with all the new items. I hope it fits.

Meanwhile this past Saturday marked the 30th workday of the 2020 season. With the help of Ben, “Bob”, Bob C., Gene, Norm, Robby, and Scott the crew installed 120 feet of track putting the passenger line project in reach of the halfway point with about 80 feet to go before it will reach the future grade crossing. Hopefully during our next workday, which is on Saturday, October 24th at 8:30 a.m. we will be able to build the necessary track panels needed to reach the halfway point. Speaking of track panels, we are needing 19 straight panels (some with used rail), two switches for the member container project, and a lot more railroad ties.

Also not pictured below Scott also put the finishing touches on the electrical in the grey container. All we need now is to add a couple of lights in the 20 foot extension and everything will be complete. Thanks Scott for taking this project on.

Speaking of track panel construction more than 450 ties where cut this week in preparation of track panel construction. Ties for the switches still need to be cut. If you have time during the week to stop by and build a few panels let Robby or Norm know.

Previous
Previous

Workday scheduled for Saturday, October 24th at 8:30 a.m.